New Building Update March 2025

We have reached a major milestone for the building project with the team from Homestead Construction handing over the keys to us as they have finished Stage one and Two of the build. The club will now need to finish off the internal fit-out and exterior roading, paving and planting work. It is bittersweet knowing…

New Building Update October

We’ve had a lot of milestones in the build project since the last club newsletter. The building is taking shape and Homestead are on track to complete stage one of the build early in the new year.  At the club open day we will be giving people the chance to take a tour around the…

Build Update – 6 August

Homestead have been making great progress on site. The prep for the slab is finishing up and the backfill of the site is well underway. Weather permitting, the slab on the south side of the building will start being poured later this week, with the rest happening over the next week. This means the project…

Build Update – 30 June

Homestead Construction Ltd are well underway with pouring the strip footings. A concrete truck convoy were in and out of the village Weds-Fri last week and they’ve made great progress ( thanks to the sun for playing its part in keeping things moving!) In a few weeks the concrete panels making up the walls/building shell…

24 June – Build Update

Mills-Albert Limited finished the earthworks, gravel rafting, and site-scaping last week. Our gravel raft foundations have been tested and ticked off by the engineers. They’ve also compacted and tidied up the tracks between the site and beach, and shaped the sand castle behind the current club. This will be mulched and stored here until it’s…

Build update: 20 May 2024

Mills-Albert Limited made good progress last week thanks to great weather, and a helping hand from our volunteer spotters. They’ve moved 57 loads of sand offsite and placed behind the old club site. They have formed the new driveway and started on the car park. Mills-Albert Limited have 3-4 weeks left of earth moving then…

Build Update: 13 April 2024 – Let the earthworks begin!

13 April 2024 Today we had a working bee on site to clear vegetation and prepare the grounds for Mills Albert to arrive and begin site scraping. Thanks team! 15 April 2024 Today, Mills Albert arrive on site to start silt fencing, building temporary pathways and other site preparations. Next week, Homestead Construction will fence…