Build update: 20 May 2024

Mills-Albert Limited made good progress last week thanks to great weather, and a helping hand from our volunteer spotters. They’ve moved 57 loads of sand offsite and placed behind the old club site. They have formed the new driveway and started on the car park.

Mills-Albert Limited have 3-4 weeks left of earth moving then Homestead Construction Ltd will takeover the site. Concrete panels are being cast at the factory as we speak.

Thanks to Monique, Lynnie, Ash, Laura, Matt, Paul and Savannah for being the spotters last week.